Question 33 - PSPO-II discussion
When should the Product Owner update the project plan?
(choose the best answer)
A.
After the Daily Scrum to ensure an accurate daily overview of project progress.
B.
The project plan must be updated prior to the Sprint Retrospective.
C.
The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.
D.
Before the Sprint Planning to know how much work will have to be done in the Sprint.