Question 48 - PSPO-II discussion
How much of the Sprint Backlog must be defined during Sprint Planning?
(choose the best answer)
A.
Enough so the Developers can create a forecast of what they can do during the Sprint.
B.
All of the potential work. Sprint Planning is not over until 100% of the work is identified and estimated.
C.
Just enough to understand design and architectural implications.
D.
Just enough tasks for the Scrum Master to be confident in the Developer's understanding of the Sprint.