When many Scrum Teams are working on the same product, should all of their Increments be combined every Sprint?
(choose the best answer)
A.
No, each Scrum Team stands alone.
B.
Yes, otherwise the Product Owner and stakeholders are unable to accurately inspect the Increment.
C.
Yes, but only for Scrum Teams whose work has dependencies.
D.
No, that is far too hard and must be done in a hardening Sprint.