List of questions
Related questions
Question 13 - C_TS422_2023 discussion
You want to use capacity availability checks for production orders. Which settings have to be made for this?
Note: There are 2 correct answers to this question.
A.
The Relevant for Finite Scheduling indicator must be set.
B.
The scope of check must be defined in Customizing.
C.
A checking rule must be assigned to the work centers.
D.
An overall profile must be assigned in the checking control.
Your answer: