Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

A.

Production orders

Answers
A.

Production orders

B.

Planned orders (firmed)

Answers
B.

Planned orders (firmed)

C.

Planned orders (unfirmed)

Answers
C.

Planned orders (unfirmed)

D.

ATP quantities

Answers
D.

ATP quantities

Suggested answer: A, B