In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

A.

Use a specific MRP list.

Answers
A.

Use a specific MRP list.

B.

Use a specific material status.

Answers
B.

Use a specific material status.

C.

Use a specific material group.

Answers
C.

Use a specific material group.

D.

Use a specific MRP type.

Answers
D.

Use a specific MRP type.

Suggested answer: B, D