ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 19 - PMI-RMP discussion

Report
Export

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

A.

The audit team

Answers
A.

The audit team

B.

The risk manager

Answers
B.

The risk manager

C.

The risk owners

Answers
C.

The risk owners

D.

The discipline engineers

Answers
D.

The discipline engineers

Suggested answer: B

Explanation:

The risk manager is responsible for ensuring that all risks, including secondary risks, are identified and addressed during the risk response planning process. If key secondary risks were missed, the risk manager should be held accountable. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, Section 11.5)

The risk manager is responsible for identifying and analyzing risks, as well as planning and implementing risk responses. Secondary risks are those risks that arise as a direct result of implementing a risk response to a specific risk. The risk manager should have considered the potential secondary risks during the risk response planning and updated the risk register accordingly.The project manager should hold the risk manager accountable for missing the secondary risks and ensure that they are properly addressed12

asked 14/11/2024
SANGEETH N
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first