List of questions
Related questions
Question 19 - PMI-RMP discussion
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
A.
The audit team
B.
The risk manager
C.
The risk owners
D.
The discipline engineers
Your answer:
0 comments
Sorted by
Leave a comment first