Question 20 - PMI-RMP discussion
.
A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)
A.
Budget variance data from previously completed projects.
B.
Project scope and cost management plans from previous projects.
C.
Lessons learned from similar completed projects.
D.
Previous project risks that may be relevant to this project.
E.
Stakeholder analysis metrics from projects with similar risk profiles.