An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

A.

Ensure sufficient resources are available

Answers
A.

Ensure sufficient resources are available

B.

Revise the risk management plan

Answers
B.

Revise the risk management plan

C.

Update the risk register

Answers
C.

Update the risk register

D.

Meet with the project's stakeholders

Answers
D.

Meet with the project's stakeholders

Suggested answer: B

Explanation:

The risk management plan is a document that describes how risk management activities will be structured and performed on a project.It defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms1.The risk management plan should be aligned with the project management plan, which defines the project scope, schedule, cost, quality, and other aspects2. When an organization decides to accelerate a key project, it means that the project objectives, assumptions, constraints, and environment have changed. This will affect the risk exposure and profile of the project, as well as the risk management approach and resources. Therefore, the first action for the project risk manager to take is to revise the risk management plan to reflect the new situation and ensure that the risk management process is still effective and efficient. Revising the risk management plan may involve updating the risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms to suit the accelerated project.The project risk manager should also communicate the revised risk management plan to the relevant stakeholders and obtain their approval and support1. Ensuring sufficient resources are available, updating the risk register, and meeting with the project's stakeholders are all important actions to take when accelerating a project, but they are not the first action. These actions should be done after revising the risk management plan, as they depend on the updated risk management approach and process.For example, the project risk manager may need to allocate more resources to risk management activities, identify and analyze new or changed risks, implement new or modified risk responses, and report the risk status and performance to the stakeholders based on the revised risk management plan1.Reference:2,1.

When a project is accelerated, the risk landscape changes. The project risk manager should first revise the risk management plan to address the new timeline and its potential impacts on the project. This will help in identifying new risks, reassessing existing risks, and updating risk responses.

asked 14/11/2024
Sascha Mintenbeck
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first