Question 23 - PMI-RMP discussion
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
What should the risk management professional do next?
A.
Perform a sensitivity analysis to the higher-level aggregate activities
B.
Develop a risk breakdown structure (RBS) identifying the potential risk categories
C.
Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis
D.
Perform a base line Monte Carlo simulation to address overall threats to project objectives
Your answer: