A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment
What should the risk manager do?
A.
Confirm the risk triggers are still valid.
B.
Ask the architect to develop acceptance criteria.
C.
Review the feature with the project team.
D.
Escalate the issue to the project board.