Question 25 - PMI-RMP discussion
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?
A.
Ask the project sponsor if every risk in the risk register can have the same priority.
B.
Mark every identified risk as an extremely high priority and any future risks as a lower priority.
C.
Agree with the SME, treat every risk with equal priority, and inform all stakeholders.
D.
Perform a sensitivity analysis and determine the correct priority of every identified risk.