A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

A.

Close the risks and update their status in the risk register.

Answers
A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

Answers
B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

Answers
C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks' severity, and update the risk register.

Answers
D.

Reevaluate those risks' severity, and update the risk register.

Suggested answer: A

Explanation:

Since the design phase is complete and the identified risks did not materialize, the project manager should close the risks and update their status in the risk register.

The project manager should close the risks that did not materialize during the design phase and update their status in the risk register. Closing risks is part of the monitor and close risks process, which involves tracking the implementation of risk responses, monitoring the residual and secondary risks, and evaluating the effectiveness of risk management throughout the project. Closing risks also involves updating the risk register with the current status of the risks, the outcomes of the risk responses, and any lessons learned from the risk management process. Updating the risk register helps to maintain an accurate and updated record of the project risks and their impacts.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.97-981

asked 14/11/2024
James Brion
37 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first