Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project's risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

A.

The risk management plan

Answers
A.

The risk management plan

B.

The risk triggers

Answers
B.

The risk triggers

C.

The risk prioritization criteria

Answers
C.

The risk prioritization criteria

D.

The portfolio management plan

Answers
D.

The portfolio management plan

Suggested answer: A

Explanation:

The risk management plan provides guidance on how often the risk register should be updated or reviewed. It takes into account the specific industry, project, and organizational context, including the business rhythm.