List of questions
Related questions
Question 84 - PMI-RMP discussion
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
A.
Review the agreed-upon risk tolerance
B.
Perform a sensitivity analysis of the risk
C.
Find out the stakeholders' risk appetite
D.
Use industry standard risk thresholds
Your answer:
0 comments
Sorted by
Leave a comment first