Question 85 - PMI-RMP discussion
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
A.
Add contingencies to other tasks to mitigate similar risks.
B.
Reassess risks with a new assumptions and constraints analysis.
C.
Review the risk response plan looking for lessons learned.
D.
Log the event in the issue log and update the project management plan.
Your answer: