List of questions
Related questions
Question 93 - PMI-RMP discussion
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board's response?
A.
Engaging the key stakeholders during the prioritization process
B.
Prioritizing the risks based on the project sponsor's risk appetite
C.
Engaging with the project sponsor before presenting to the board
D.
Working with an established industry standard prioritization method
Your answer:
0 comments
Sorted by
Leave a comment first