List of questions
Related questions
Question 94 - PMI-RMP discussion
A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.
What should the risk manager do next?
A.
Start a quantitative analysis to understand the impact.
B.
Crash the schedule to mitigate the risk consequences.
C.
Transfer the risk to the external team.
D.
Ask the risk owners to review the risk response plan.
Your answer:
0 comments
Sorted by
Leave a comment first