Question 99 - PMI-RMP discussion
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
What will help calculate the impact?
A.
Risk analysis
B.
Risk identification
C.
Risk treatment
D.
Risk evaluation
Your answer: