A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
A.
Develop an affinity diagram
B.
Perform the analytical hierarchy process
C.
Perform a SWOT analysis
D.
Assign probability and impact