Question 101 - PMI-RMP discussion
A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
A.
Sensitivity analysis
B.
What-if scenario analysis
C.
Regression analysis
D.
Decision tree analysis
Your answer: