Question 105 - PMI-RMP discussion
After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.
What should the risk manager do to facilitate the sponsor's ask?
A.
Monte Carlo analysis
B.
Qualitative risk analysis
C.
Sensitivity analysis
D.
Quantitative risk analysis
Your answer: