During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.
How should the risk manager handle this situation?
A.
Request for a skilled facilitator to help resolve conflicts that have arise.
B.
Refer to the team's ground rules on how to resolve conflicts.
C.
Run a sensitivity analysis to check which risks have the most impact.
D.
Use the assumption analysis techniques to validate the assumptions.