Question 103 - PMI-RMP discussion
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints
What should the project manager do next to determine risk impact of assumptions and constraints?
A.
Add all assumptions and constraints to the risk register.
B.
Add the risk impact of the assumptions in the risk register.
C.
Add the assumptions and constraints to the assumption log.
D.
Add the assumptions and constraints in the project charter.