A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

A.

Evaluating the project's probability of success

Answers
A.

Evaluating the project's probability of success

B.

Identifying threats and opportunities

Answers
B.

Identifying threats and opportunities

C.

Evaluating the project's impact

Answers
C.

Evaluating the project's impact

D.

Performing a qualitative analysis

Answers
D.

Performing a qualitative analysis

Suggested answer: B

Explanation:

The main output of the stakeholder meeting in the initiation phase is to identify threats and opportunities that may impact the project in a positive or negative way. This information will be used to develop the risk management plan.

The meeting that the project stakeholders are invited to in the initiation phase is part of the Identify Risks process. The purpose of this process is to identify the risks that may affect the project objectives in a positive or negative way, and to document their characteristics. The main output of this process is the risk register, which is a document that contains the list of identified risks, their causes, potential responses, and other relevant information. The risk register is an essential input for the subsequent risk management processes, such as Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, and Monitor Risks. Therefore, the correct answer is B. Identifying threats and opportunities.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 79-80, 86-87.