When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

A.

Select the strategies with the least overall impact to resources.

Answers
A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

Answers
B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

Answers
C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Answers
D.

Select the strategies with the greatest benefit to stakeholders.

Suggested answer: C

Explanation:

The overall goal of selecting strategies during the Plan Risk Response activity is to choose those strategies that have the greatest overall positive influence on the project, considering factors such as cost, schedule, and resources.

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Responseis to select risk response strategies based on the risk appetite and tolerance of the organization and stakeholders1. The overall goal of selecting risk response strategies is to select the strategies with the greatest overall positive influence on the project objectives, such as scope, schedule, cost, quality, etc.The risk response strategies should aim to enhance the opportunities and reduce the threats to the project, while considering the cost-benefit analysis, the feasibility, and the alignment with the project goals and stakeholder expectations2.The risk response strategies should not be selected based on the least overall impact to resources, because that may not be the most effective or efficient way to address the risks, and it may ignore the potential benefits of some strategies that may require more resources but also deliver more value3. The risk response strategies should not be selected based on the least financial impact, because that may not be the most relevant or comprehensive criterion to evaluate the risks, and it may overlook other aspects of the project, such as quality, customer satisfaction, reputation, etc.that may also be affected by the risks4.The risk response strategies should not be selected based on the greatest benefit to stakeholders, because that may not be the most realistic or achievable goal, and it may create conflicts or trade-offs among different stakeholder groups that may have different or competing interests, needs, and expectations5.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4403: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4414: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4425: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 518.

asked 14/11/2024
Andrej Mišura
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first