Question 131 - PMI-RMP discussion
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
A.
Brainstorming
B.
Delphi method
C.
Focus group
D.
Checklist analysis