As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
A.
Close and communicate the results of the risk response actions.
B.
Run a workshop to analyze the effectiveness of the risk plan.
C.
Conduct a risk reserve analysis and document the results.
D.
Verify that all risk response actions have been documented.