As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

A.

Close and communicate the results of the risk response actions.

Answers
A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

Answers
B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

Answers
C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented.

Answers
D.

Verify that all risk response actions have been documented.

Suggested answer: A