Question 134 - PMI-RMP discussion
In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.
In implementing this plan, which response should the risk manager use?
A.
Exploit
B.
Accept
C.
Share
D.
Enhance
Your answer: