Related questions











Question 134 - PMI-RMP discussion

Report
Export

In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

A.

Exploit

Answers
A.

Exploit

B.

Accept

Answers
B.

Accept

C.

Share

Answers
C.

Share

D.

Enhance

Answers
D.

Enhance

Suggested answer: A