Question 135 - PMI-RMP discussion
During project development, a risk manager notices that a major update in the country's regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.
Which tool should the project team use to determine this?
A.
Sensitivity analysis
B.
Threshold analysis
C.
Reserve analysis
D.
Strengths, weaknesses, opportunities, and threats (SWOT) analysis
Your answer: