List of questions
Related questions
Question 136 - PMI-RMP discussion
Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?
A.
Use the information for a risk workshop.
B.
Improve monitoring and controlling of activities.
C.
Document the issues in the lessons learned.
D.
Create an issue log to share with the team.
Your answer:
0 comments
Sorted by
Leave a comment first