In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder's decision regarding the project?

A.

Perform a risk impact analysis.

Answers
A.

Perform a risk impact analysis.

B.

Perform a risk reserve analysis.

Answers
B.

Perform a risk reserve analysis.

C.

Perform a procurement analysis.

Answers
C.

Perform a procurement analysis.

D.

Perform a stakeholder impact and influence analysis.

Answers
D.

Perform a stakeholder impact and influence analysis.

Suggested answer: D

Explanation:

A stakeholder impact and influence analysis is a technique to identify the level of interest and power of each stakeholder, and to assess how they may affect or be affected by the project outcomes. It can help the risk manager to understand the stakeholder's perspective and expectations, and to communicate with them effectively. In this case, the risk manager should perform a stakeholder impact and influence analysis to understand why the major investor is about to drop their intention to continue executing the project, and to address their concerns and needs.A risk impact analysis, a risk reserve analysis, and a procurement analysis are not relevant to the stakeholder's decision, and would not help the risk manager to understand their rationale.Reference: PMI Risk Management Professional (PMI-RMP) Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP) Cert Guide3