A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

Answers
A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

Answers
B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

Answers
C.

Decision tree analysis

D.

Cost-benefit analysis

Answers
D.

Cost-benefit analysis

Suggested answer: C