A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the client's vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

A.

Enhance risk identification.

Answers
A.

Enhance risk identification.

B.

Review the contingency reserves.

Answers
B.

Review the contingency reserves.

C.

Create a risk response plan.

Answers
C.

Create a risk response plan.

D.

Review the risk registry.

Answers
D.

Review the risk registry.

Suggested answer: D

Explanation:

The risk registry is a document that records the identified risks, their characteristics, their status, and their responses. It is a key input for risk management and a source of information for project stakeholders. The risk manager should review the risk registry first to understand the current state of the project risks, especially the ones related to the client's vendor, and to evaluate the effectiveness of the risk responses implemented so far. Enhancing risk identification, reviewing the contingency reserves, and creating a risk response plan are possible actions that the risk manager may take after reviewing the risk registry, but they are not the first thing to do.

Reference: PMI Risk Management Professional (PMI-RMP) Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP) Cert Guide3