Question 141 - PMI-RMP discussion
A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the client's vendor, which apparently has been causing all of the issues.
What should the risk manager do first?
A.
Enhance risk identification.
B.
Review the contingency reserves.
C.
Create a risk response plan.
D.
Review the risk registry.
Your answer: