List of questions
Related questions
Question 142 - PMI-RMP discussion
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
Accept the identified risk because other stakeholders feel that there are higher priority risks to address.
Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.
Escalate the identified risk to the project sponsor and allow them to determine the best course of action.
Add the identified risk to the risk register for future probability and impact analysis.
0 comments
Leave a comment first