Question 143 - PMI-RMP discussion
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
A.
The risk categorization
B.
The risk simulation
C.
The full risk description
D.
The risk response plan
Your answer: