While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.
What should the risk manager do to manage this risk?
A.
Perform time recovery actions.
B.
Execute the prevention plans.
C.
Execute the contingency plans.
D.
Perform change management.