While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

A.

Perform time recovery actions.

Answers
A.

Perform time recovery actions.

B.

Execute the prevention plans.

Answers
B.

Execute the prevention plans.

C.

Execute the contingency plans.

Answers
C.

Execute the contingency plans.

D.

Perform change management.

Answers
D.

Perform change management.

Suggested answer: C

Explanation:

Contingency plans are predefined actions that the project team will take if an identified risk event occurs. They are designed to reduce the impact or probability of the risk, or to restore the project to its original objectives. Contingency plans are part of the risk response planning process, and they should be documented in the risk register. In this case, the risk manager should execute the contingency plans to deal with the delays caused by the weather, as they cannot be avoided or mitigated. Performing time recovery actions, executing prevention plans, or performing change management are not appropriate responses for this risk, as they are either reactive, proactive, or corrective measures that do not address the risk directly.Reference: = PMBOK Guide, 6th edition, page 443; The Standard for Risk Management in Portfolios, Programs, and Projects, page 75.