Question 146 - PMI-RMP discussion
A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.
What should the risk manager advise the project team to do?
A.
Align the project risk thresholds with the risk appetite of a critical region.
B.
Align the project risk thresholds with the organizational risk appetite.
C.
Concentrate on the risk appetites of the influential stakeholders.
D.
Concentrate on the risk appetites of the vulnerable stakeholders.