While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

A.

Remind the project team to keep an open mind

Answers
A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

Answers
B.

Review the results with the project manager afterward

C.

Review published operational experience reports

Answers
C.

Review published operational experience reports

D.

Use the mean answers provided by the project team

Answers
D.

Use the mean answers provided by the project team

Suggested answer: C