In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

A.

Document the concern over the potential excessive additional cost.

Answers
A.

Document the concern over the potential excessive additional cost.

B.

Manage the potential excessive additional cost as a new risk.

Answers
B.

Manage the potential excessive additional cost as a new risk.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

Answers
C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

Answers
D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

Suggested answer: B