ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 149 - PMI-RMP discussion

Report
Export

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

A.

Remove the activity padding.

Answers
A.

Remove the activity padding.

B.

Review the risk response plan.

Answers
B.

Review the risk response plan.

C.

Update the risk contingency plan.

Answers
C.

Update the risk contingency plan.

D.

Update the schedule constraints.

Answers
D.

Update the schedule constraints.

Suggested answer: C
asked 14/11/2024
Penny Chang
47 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first