Question 149 - PMI-RMP discussion
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.
What should the risk manager do first?
A.
Remove the activity padding.
B.
Review the risk response plan.
C.
Update the risk contingency plan.
D.
Update the schedule constraints.