Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate. This is an example of what?

A.
Breach of contract
Answers
A.
Breach of contract
B.
Issue
Answers
B.
Issue
C.
Risk
Answers
C.
Risk
D.
Claim
Answers
D.
Claim
Suggested answer: D