Question 19 - PgMP discussion

Report
Export

You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

A.
Parkinson's Law
Answers
A.
Parkinson's Law
B.
Law of Diminishing Returns
Answers
B.
Law of Diminishing Returns
C.
80/20 Law
Answers
C.
80/20 Law
D.
Pareto's Law
Answers
D.
Pareto's Law
Suggested answer: A
asked 23/09/2024