What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

A.
Project Management Information System
Answers
A.
Project Management Information System
B.
Integrated Change Control
Answers
B.
Integrated Change Control
C.
Scope Verification
Answers
C.
Scope Verification
D.
Configuration Management System
Answers
D.
Configuration Management System
Suggested answer: D