Question 23 - PgMP discussion

Report
Export

Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

A.
Quality Management System
Answers
A.
Quality Management System
B.
Change Control System
Answers
B.
Change Control System
C.
Project Management Information System
Answers
C.
Project Management Information System
D.
Integrated Change Control System
Answers
D.
Integrated Change Control System
Suggested answer: C