Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?
A.
Quality Management System
B.
Change Control System
C.
Project Management Information System
D.
Integrated Change Control System