Question 29 - PgMP discussion

Report
Export

You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for which one?

A.
A forklift
Answers
A.
A forklift
B.
Materials for the installation of a new server
Answers
B.
Materials for the installation of a new server
C.
A positive risk response
Answers
C.
A positive risk response
D.
Gary, an application developer
Answers
D.
Gary, an application developer
Suggested answer: C