List of questions
Related questions
Question 30 - PgMP discussion
Your program has been selected and its program charter is now being created. The program charter defines all of the following characteristics except for which one?
A.
Program constraints
B.
Program scope
C.
High-level objectives for the program
D.
Project scope statement for all projects within the program
Your answer:
0 comments
Sorted by
Leave a comment first