Terri is the program manager for her organization and she's working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

A.
Add the change to the program scope herself, as she is a project manager
Answers
A.
Add the change to the program scope herself, as she is a project manager
B.
Add the change request to the scope and complete integrated change control
Answers
B.
Add the change request to the scope and complete integrated change control
C.
Document the change request in a change request form.
Answers
C.
Document the change request in a change request form.
D.
Create a change request charter justifying the change request
Answers
D.
Create a change request charter justifying the change request
Suggested answer: C