Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?
A.
Resource network diagram
B.
Resource breakdown structure
C.
Resource histogram
D.
Pareto chart