Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

A.
Lead time
Answers
A.
Lead time
B.
Crashing
Answers
B.
Crashing
C.
Lag time
Answers
C.
Lag time
D.
Fast tracking
Answers
D.
Fast tracking
Suggested answer: B