Question 51 - PgMP discussion
Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?
A.
Lead time
B.
Crashing
C.
Lag time
D.
Fast tracking